Daytime Noise Monitoring Results                    
                           
Station M5, Chuk Lam Ming Tong                    
Date Start Time End Time  Weather Noise level (dB(A)), 30 min Major Construction Noise Source(s) Observed Other Noise Source(s) Observed Remarks Temp. (°C) Wind Speed (m/s) Noise Meter Model / ID Calibrator Model / ID
Leq L10 L90
06-Jan-10 13:33 14:03 Cloudy 68 71 65 Operation of hydraulic excavator and mobile crane Maintenance works at neighbour building and Chuk Lam Ming Tong;
Construction noise (by Hong Kong Electric) near the site entrance.
N.A   <5 B&K 2238   S/N : 2684503 B&K 4231  S/N: 2385180
12-Jan-10 14:33 15:03 Cloudy 65 68 60 Operation of mobile crane Maintenance works at neighbour building and Chuk Lam Ming Tong;
Road traffic noise.
N.A   <5 B&K 2238   S/N : 2684502 B&K 4231  S/N: 2385180
22-Jan-10 09:56 10:26 Cloudy 66 68 62 Operation of mobile crane Maintenance works at neighbour building;
Road traffic noise.
N.A   <5 B&K 2238   S/N : 2684503 B&K 4231  S/N: 2385180
27-Jan-10 13:31 14:01 Cloudy 67 69 64 Operation of hydraulic excavator Maintenance works at neighbour building and Chuk Lam Ming Tong;
Road traffic noise.
N.A   <5 B&K 2238   S/N : 2684503 B&K 4231  S/N: 2385180
      Min. 65                  
      Max. 68